Last updated: December 7, 2023
** Disclaimer: These are the stages of the construction. The Rajagopuram temple will open once the Kumbhabhishekam has taken place.
Phase I
September 2022 – March 2024

Exterior work commencement
With the Devi’s grace, over 60% of Phase 1’s local construction and the Ganapati Sannidhi construction has been completed. The foundation was completed in November 2022. Now, construction of the outer structure is ongoing. The Ganapati Sannidhi has shipped from India and is expected to be delivered in Rochester in December. The manufacturing of the fiberglass outer component will take place in Mumbai and shipped to Rochester within the next six months.
Foundation Work
Enclosing walls
Fiberglass sidings on west wall
Ganapati Sannidhis
Exterior work completion
The Subramanya Sannidhi construction is currently ongoing in Devakottai. About 50% of the work has been completed.
Complete enclosing walls
Complete fiberglass sidings on remaining walls
Murugan Sannidhi & Vigraham
Phase II
March 2024 – December 2024
Phase III
January 2025 – December 2025
Interior work commencement
East Gopuram
Devi Sannidhi
Interior work completion
Remaining Gopurams
Shiva Sannidhi
Navagraha Sannidhi
Phase IV
January 2026 – December 2026
Phase V
January 2027 – December 2027
Subsidiaries
Remaining Sannidhis
Kumbhabhishekam

Phase VI
2028