Last updated: December 7, 2023
** Disclaimer: These are the stages of the construction. The Rajagopuram temple will open once the Kumbhabhishekam has taken place. 

Phase I

September 2022 – March 2024

Exterior work commencement

With the Devi’s grace, over 60% of Phase 1’s local construction and the Ganapati Sannidhi construction has been completed. The foundation was completed in November 2022. Now, construction of the outer structure is ongoing. The Ganapati Sannidhi has shipped from India and is expected to be delivered in Rochester in December. The manufacturing of the fiberglass outer component will take place in Mumbai and shipped to Rochester within the next six months.

  • Foundation Work

  • Enclosing walls

  • Fiberglass sidings on west wall

  • Ganapati Sannidhis

Exterior work completion

The Subramanya Sannidhi construction is currently ongoing in Devakottai. About 50% of the work has been completed. 

  • Complete enclosing walls

  • Complete fiberglass sidings on remaining walls

  • Murugan Sannidhi & Vigraham

Phase II

March 2024 – December 2024

Phase III

January 2025 – December 2025

Interior work commencement

  • East Gopuram

  • Devi Sannidhi

Interior work completion

  • Remaining Gopurams

  • Shiva Sannidhi

  • Navagraha Sannidhi

Phase IV

January 2026 – December 2026

Phase V

January 2027 – December 2027

Subsidiaries

  • Remaining Sannidhis

Kumbhabhishekam

Phase VI

2028