Construction Progress Update – Aug 2021

The temple house foundation removal, fill and compaction has been completed under the supervision of Sickles Corp.  The excavation for the water bodies to the south of the temple has also been completed. A new kind of Deer(e) can be spotted on the temple grounds :).

We have received drawings of Foundation and Structural from Ashok and are currently under our team review. Then, we plan to bid the package out to at least 3 pre-qualified construction contractors. The relocation & re-installation of the parking lot / exterior lighting poles will be executed by a reputed local electrical contractor from the Rochester area and completed prior to the start of winter. 